Saturday, 29 September 2018

Rain ..... Its good for the Garden

Pitter patter, drip, drip drip…. The welcome sound of rain on the roof of the tin shed.  The usual Winter long dry spell now appears to be broken! 

A few days earlier, we had enjoyed the briefly flashy splendour of a fast-moving thunderstorm. But there was really nothing in it.  Just a half-hearted attempt by the weather gods to get us excited over the prospect of rain.

But this is Queensland and the start of the storm season, so we knew that rain would soon be upon us.  And today it has arrived!  A day long steady stream of ground soaking rain, in dispersed with the occasional heavy downpours.

In the morning we scampered out to the orchard to quickly plant a new fig tree. There was no need to use a watering can, the rain soon watered it in.  However, whilst the garden will benefit from the rain, not all creatures are welcoming the weather.


This soaked Koala and her joey, do not seem as impressed as we are!






Jen and Rog
Email:  honeydaleqld@gmail.com

Thursday, 27 September 2018

The First Sod Turned



On the 19 of September 2018 the HSTP contractor arrived at 6:30 am with his bob cat and 10 Tonne excavator, and as we had already marked out the ground he got started.  The aim was to get the hole for the Home Sewerage Treatment Plant dug by 8:30 am so it could be off loaded and positioned.  Luck was not with us as at 500 mm down he hit rock.

Breaking Rock

The contractor was prepared and had a rock breaker with him and he started.  At 8:30 am the HSTP arrived and there was no choice but of off load it out of the way.   After 8 long and noisy hours he got the hole down to depth.  We got out the instruments and checked the depth and we all decided it was time to knock off due to the fading light.
The HSTP Plant 

The next morning we started at 6:30 am by re-checking the depth, it is easy to make a mistake when you are tired.  Satisfied with the depth the contractor placed bedding gravel and checked that the bedding was level.  He finished just in time as the crane to place the HSTP arrived, so the rigger started slinging it.  By 10:30 am the HSTP was in place and back filling was underway.

The Finished Excavation for the HSTP
The next task was to trench from the HSTP to the Granny Flat and onto the House.  We then ran the conduits and the power cable for the HSTP on one side of the trench,  The HSTP contractor ran the sewer lines on the other side of the trench.  We all stopped for some lunch and water when the council inspector arrived and gave his seal of approval.  We started backfilling almost immediately.
Positioning the HSTP

After the back filling was completed the HSTP contractor levelled the ground where the granny flat rainwater tanks would be installed.  The HSTP contractor loaded his equipment under lights.  It was a long day.
Part of the Trenches

We did not get much rest as the rainwater tanks were due in a week’s time and the tank stand had to be completed by then.  A full day was needed to move all the spoil out of the way and clean up the area around the tank stand.  Both of us then spent the next day placing the sleepers and getting the levels right.  Any error at this stage would be compounded over the next few days.
Framing the Rain Water Tank Stand
The sleepers were then bolted together and one removed so that cracker dust could be placed and compacted with our little tractor.  The final sleeper was bolted in place and the pad brought to approximate level.

Off Loading the Second Tank
Using a 3 m screed and a 1.2 spirit level the tank stand was levelled off.  This was a tedious task that took the best part of an afternoon.  The next morning the location details were checked against the council approved plans and we used instruments to check that the tank stand was level, which it was.

Positioning the Tanks
Our tanks arrived on time.  Unloading was a basic process; some pieces of wood were placed on the tank stand and the tanks were pushed off the truck on to the wood.  The tanks slid easily on the wood so the tanks were placed in the desired locations and the wood removed.  Within an hour of arrival the tanks were in place.

Tanks in Final Position
All that was left was to install the tank fittings and put some rain water into the tanks to ensure that they remain in place.




Jen and Rog
Email:  honeydaleqld@gmail.com

Tuesday, 18 September 2018

Work Has Started on the Granny Flat


After months of work and the involvement of many consultants we obtained council approval and permits to start work.  The process we went through included soil test consultants, bushfire consultants, energy efficiency consultants, civil engineers and designers.  We also engaged a consultant to help us prepare the Development Application.  The Council queried us about land clearing but we were able to respond without engaging another consultant as we were not planning to clear any land.
Apart from the paperwork we also had to remove all the rubbish from the Granny Flat pad.   This required a lot of trips to the local tip.
We also needed to cut down and chip a large stand of lantana.  The lantana was covering a large fallen tree.  The tree was cut up and taken away, and the trunk yielded several fine slabs for milling to be used in the Granny Flat.
Part of the bushfire management procedure required that all ground litter within a 20 meter radius of the granny flat must also removed.  There was a lot of dead wattle but the larger trees could remain. 
Removing the rubbish, cutting out the weeds and clearing all the dead timber took many days of hard work.  But it has been worth the effort as can be seen in the before and after photos.

After - View to the North

View to the South

View to the West


Jen and Rog
Email:  honeydaleqld@gmail.com